AUGMENTATION TO MALEGAON WSS, DIST. NASHIK

 

              The scheme is administratively approved for Rs. 7830 lakhs on 19.3.1998   and technically sanctioned on 4.5.1998. The source of the scheme is head works in the submergence of the Girna Dam. The designed capacity of the scheme is 71 MLD. The population of 5,50,000 souls of the Malegaon city will be supplied water @ 135 LPCD after completion of the scheme.

 

              At present 19.06% works are completed. The scheme is expected to be completed by 2005 year. The up-to-date expenditure incurred on the scheme is Rs. 1500 Lakhs.

 

PRESENT STATUS OF URBAN WSS, NASHIK DISTRICT

 

 

Sr.No

Name of  Town

Source

Population  2001

GOI Norm

Normal Lpcd

Summer Lpcd

1

Bhagur

Darna River

12454

70

65

48

Aug. scheme is in progress.

2

Igatpuri

Talegaon Dam & Municipal dam

31572

70

70

40

Work of Aug. scheme is in progress.

3

Manmad

Palkhed

72412

100

55

30

-

4

Sinnar

Darna River

32727

70

55

40

 Aug.  scheme

In progress.

5

Trimbak

Amboli Dam

9804

70

90

90

Sinhasth work is under progress.

6

Yeola

Palkhed , L.B.Canal.

43205

70

60

50

Aug.  in progress.

7

Satana

Kelzar Dam

32551

70

55

40

Aug.  is progress.

8

Malegaon

Girna Dam

409190

135

60

50

Aug. is progress.

9

Nandgaon

Dahegaon Dam & Girna Dam

23191

70

60

25

-

10

Nashik muncipal Corpor-ation

Gangapur Dam, Darna Dam

1076967

150

150

130

The work of Aug. scheme is in under progress and executed by the Nashik Municipal Corporation.