AUGMENTATION TO MALEGAON WSS, DIST. NASHIK
The scheme is administratively approved for Rs. 7830 lakhs on 19.3.1998 and technically sanctioned on 4.5.1998. The source of the scheme is head works in the submergence of the Girna Dam. The designed capacity of the scheme is 71 MLD. The population of 5,50,000 souls of the Malegaon city will be supplied water @ 135 LPCD after completion of the scheme.
At present 19.06% works are completed. The scheme is expected to be completed by 2005 year. The up-to-date expenditure incurred on the scheme is Rs. 1500 Lakhs.
PRESENT STATUS OF URBAN WSS, NASHIK DISTRICT
|
Sr.No |
Name of Town |
Source |
Population 2001 |
GOI Norm |
Normal Lpcd |
Summer Lpcd |
|
|
1 |
Bhagur |
Darna River |
12454 |
70 |
65 |
48 |
Aug. scheme is in progress. |
|
2 |
Igatpuri |
Talegaon Dam & Municipal dam |
31572 |
70 |
70 |
40 |
Work of Aug. scheme is in progress. |
|
3 |
Manmad |
Palkhed |
72412 |
100 |
55 |
30 |
- |
|
4 |
Sinnar |
Darna River |
32727 |
70 |
55 |
40 |
Aug. scheme In progress. |
|
5 |
Trimbak |
Amboli Dam |
9804 |
70 |
90 |
90 |
Sinhasth work is under progress. |
|
6 |
Yeola |
Palkhed , L.B.Canal. |
43205 |
70 |
60 |
50 |
Aug. in progress. |
|
7 |
Satana |
Kelzar Dam |
32551 |
70 |
55 |
40 |
Aug. is progress. |
|
8 |
Malegaon |
Girna Dam |
409190 |
135 |
60 |
50 |
Aug. is progress. |
|
9 |
Nandgaon |
Dahegaon Dam & Girna Dam |
23191 |
70 |
60 |
25 |
- |
|
10 |
Nashik muncipal Corpor-ation |
Gangapur Dam, Darna Dam |
1076967 |
150 |
150 |
130 |
The work of Aug. scheme is in under progress and executed by the Nashik Municipal Corporation. |