Maharashtra Jeevan PradhikaranAdditional 50 MLD Scheme for Mira-Bhayander Corporation 2/5/03 |
| |
|
|
|
|
| ESR at Navghar.jpg | Gravity Main.jpg | MBR at Patlipada... | Pipeline Bridge.jpg | Road Crossing.jpg |
1. 31.3.1997 2. Date
of start 10/1998 3. Sanctioned
Cost Rs.110.64
Crores. 4. Date
of Commissioning Partly
commissioned from 24.5.2001. 5. Completion
Cost of the Project Expdt.
upto 31.12.2002 Rs. 6. Supply
in LPCD before commissioning 60
LPCD 7. Supply
in LPCD after commissioning 123LPCD 8. i)
400 HP
– 1 No. Raw Water Pumping Machinery at Shahad ii)
50 MLD
Water Treatment Plant at Temghar. iii)
900
H.P. – 1 No. Pure Water Pumping Machinery at
Temghar. iv)
15 ML
MBR at Mankoli. v)
2000mm
dia M.S. Pure Water Gravity Main from Mankoli Junction to MIDC Bridge.
L=6.25 Kms. vi)
1350mm
dia M.S.Pure Water Gravity Main from Majiwade to Patlipada. L= 4.56
Kms. vii)
2.5 ML
Elevated Sump at Patlipada. viii)
200 HP
– 3 Nos. Pure Water Pumping Machinery at Patlipada. ix)
5 ML
MBR at Patlipada. x)
1350mm
dia Pure Water Rising Main from 2.5 ML Sump to 5 ML MBR. L = 90
m. xi)
1350/941mm
dia M.S. Pure Water Gravity Main from Patlipada to Bhayander. L= 16.72
Kms. xii)
RCC
ESR in Bhayander – 8 Nos. Having capacity 0.8 ML to 2.5
ML. xiii)
RCC
Sump and Pump House in Bhayander – 9 Nos. Having capacity 0.8 ML to 4.5
ML. xiv)
Pure
Water Pumping Machinery at Bhayander for 10 ESRs 40 HP to 100
HP. xv)
150mm to 700 mm dia CI/MS Distribution System. L =
55.17
Kms. Mira
Bhayander Muncipal Corporation having population 5,20,000
Souls.
Date of Administrative Approval
Description of Sub work in short :-
9.
Beneficiaries