Present position of water supply schemes is as per Bruhat Arakhada
Villages
Wadi
Total Villages/Wadies in the District
758
190
Total Village/Wadies Tackled upto 31-3-96
397
154
Problematic Villages/Wadies after 1-4-96
361
36
Villages deleted due to sufficient water available or other reason
1
0
Balance problematic villages/wadies in the district
360
36
Agencywise position
MJP
217
12
ZP
56
1
GSDA
87
23
Position of the villages/wadies to be tackled by MJP (As per Bruhat Arakhada)
Schemes completed up to 31-3-2002
39
0
Schemes in progress
178
12
Scheme sanctioned but yet to be started
-
-
Schemes under preparation with new norms
0
0
Position of schemes in progress
No. of schemes
48
-
No. of villages/wadies included
182
12
Sanctioned estimated cost (in crores)
136.769
-
Upto date expenditure (in crores)
56.72
-
Expenditure required for completion (in crores)
80.049
Position of Loan sanctioned (Hudco/LIC/Nabard etc.)
No. of schemes
4
-
No. of villages/wadies included
70
6
Sanctioned estimated cost (in crores)
56.13
-
Upto date expenditure (3/02)(in crores)
34.73
-
Loan sanctioned
Hudco
25.10
-
LIC
-
-
Nabard
-
-
Others
-
-
Expenditure against loan
Hudco
LIC
Nabard
Others
Regions
|
Amaravati
|
Aurangabad
|
Konkan
|
Nagpur
|
Nashik
|
Pune
|